Projects

Major projects with their stakeholders, status and timeline — and what they mean for suppliers.

Under constructionParamaribo (Nieuwe Haven and port access)

Improving Transport Logistics and Competitiveness in Suriname (ITLCS)

IDB-financed programme (US$45 million, approved 10 July 2019) for port infrastructure and logistics in Paramaribo. Contracts signed on 16 November 2023 cover a logistics centre at …

Timeline: Approved Jul 2019; works contracts Nov 2023; bridge opened Mar 2025; programme to 2027 (government)
Final investment decisionBlock 58, offshore Suriname (~150 km from the coast)

GranMorgu (Block 58)

Suriname's first offshore oil development: the Sapakara and Krabdagu fields on Block 58, produced through a 220,000 barrels-per-day FPSO. Final investment decision 1 October 2024; …

Timeline: FID Oct 2024 · first oil expected 2028 (mid-2028 per Sept 2026 reports)
TenderingReeberg, Suriname

Reeberg Block 3B Housing Development

Government housing-infrastructure project tendered as a design-and-build contract through international competitive bidding, financed under Suriname's 2026 Social Bond.

Timeline: Bids due 4 Nov 2026
TenderingSuriname (multiple sites)

Priority Social Projects Programme (Social Bond 2026)

Programme of social expenditures and priority social projects financed by the Social Bond Suriname issued in February 2026 — including school renovations, school equipment and furn…

Timeline: Notices published Jul–Sep 2026
OperationalBrokopondo / Saramacca districts

Rosebel & Saramacca gold mines

Large-scale gold operations owned by Zijin Mining since 2023. The Rosebel mine began production in 2004; Saramacca in the second half of 2020.

OperationalEastern Suriname

Merian gold mine

Large-scale gold mine developed from 2016 by the Suriname government, Newmont and Surgold; Staatsolie holds 25% on behalf of the government.

Under constructionSaramacca Canal (Paramaribo–Saramacca)

Saramacca Canal System Rehabilitation Project

World Bank-financed rehabilitation of the Saramacca Canal system, including the Doorsteek lock and sluices and canal maintenance. Contracts have been awarded to PowerChina Jiangxi …

Timeline: Works contracts awarded 2023–2024
AnnouncedFormer Suzannasdaal plantation, Commewijne

DP World offshore supply base, Suzannasdaal (Commewijne)

A 50-hectare offshore supply base for the Guyana–Suriname basin with a 500 m quay and 8.5 m guaranteed depth, on the former Suzannasdaal plantation in Commewijne. Groundbreaking on…

Timeline: Groundbreaking Aug 2022; phase 1 targeted end-Q2 2023 (current status unverified)
Under constructionEstuary of the Suriname and Commewijne rivers

Comport offshore supply base (Commewijne)

Offshore supply base being developed by Commewijne Port Facility N.V. at the estuary of the Suriname and Commewijne rivers, with land for an offshore supply and services zone. Kers…

Timeline: Under construction (industry reporting); Kersten 50% stake 2025
Under constructionRode Kruislaan 22, Paramaribo

Ministry of Health headquarters, Rode Kruislaan 22 (Paramaribo)

New building for the Ministry of Health and the Public Health Bureau (BOG), built by The 23rd Metallurgical Construction Group under the IDB-financed Health Services Improvement Pr…

Timeline: Contract Aug 2023; groundbreaking Oct 2023; completion not verified
Under constructionBrokopondo district (incl. Pokigron)

EBS solar-hybrid mini-grids (Brokopondo, Pokigron)

Solar-hybrid power for communities in Brokopondo district, financed under the IDB's Consolidating a Sustainable Energy Sector programme (US$30 million) with EBS as executing agency…

Timeline: Awards 2022–2024; commissioning not verified